Sarens CC2800-1 Helps Revamp The LNG Plant In Algeria

Sponsored By Sarens28 April 2021

Sarens performs heavy lifts at the LNG plant in Arzew, Algeria

Movement and lifts in a live petrochemical site with space constraint

involves meticulous planning and Sarens is a reference in the heavy lift and specialised transport for the Oil & Gas and Petrochemical sector.

Sarens was asked by our client Renaissance for Airproduct to execute heavy lifts and installation of refinery equipment at the LNG plant in Arzew, Algeria.

Sarens had to lift the Coldbox, lox tank, lin tanks, and other equipment. The most important component was the 47m long cold box weighing 150T. The team decided to deploy:

  • CC2800-1 with SSL 72m main boom length
  • QUY260

The main crane was selected keeping in mind the length of the 47m long cold box which was the most critical section to be lifted. The equipment was transported from Sarens yard in Algeria and was assembled in 4 days.

The heavy lifts are part of the revamp of the LNG plant built in the 1970s. This project will help reduce maintenance costs, reduce gas consumption rates, and maintain LNG gas production at the GL1Z plant.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Latest News
SC&RA elects 2021-2022 leadership
SC&RA has announced its leadership slate for 2021-2022, led by new president Kevin Johnston, of J&R Engineering.
Manitex Q1 results: increased sales, $107 million backlog
Manitex International reports backlog is at a five-year high.
40 tonne tele crawler new from Liebherr
The LTR 1040 is a new light version of the manufacturer’s 60 tonne telescopic boom crawler crane
CONNECT WITH THE TEAM
Alex Dahm Editor, International Cranes and Specialized Transport Tel: +44(0) 1892 786 206 E-mail: alex.dahm@khl.com
Mike Posener Sales Manager Tel: +353 860 431 219 E-mail: mike.posener@khl.com
CONNECT WITH SOCIAL MEDIA