Sarens Transrig loadout

22 May 2008

Sarens Transrig in Norway loaded out the 10,700 tonne topside of the first Aker H.6-e drilling rig, Aker Spitsbergen in Norway. Some 448 SPMT axles were used, along with the company's ballast system and a range of supporting material for the operation.

Immediately after the load-out, the barge was positioned in an 8 SMLT (Sarens Modular Lifting Tower) set-up and the module was lifted to a height of about 34 m. The hull was then brought under and the deck was mated with it.

The combination of weight, dimensions and height made it one of the most extreme heavy lift operations ever executed, said the company. “The lifting system in the given configuration is designed for a lifting capacity of 14,400 tonnes and to withstand a full Norwegian winter storm,”

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Long Reads
Post-pandemic demand lengthens delivery times for construction equipment
Government stimulus measures following the global pandemic have led to a surge in demand for construction equipment
Technology paves the way for driving 3D development
What is 3D modelling and what is it used for? Discover more at SC&RA Workshop
PREVIEW: SC&RA Crane & Rigging Workshop
The 2021 Crane & Rigging Workshop will be held September 14-16 at the Hyatt Regency Chicago, USA
CONNECT WITH THE TEAM
Alex Dahm Editor, International Cranes and Specialized Transport Tel: +44(0) 1892 786 206 E-mail: alex.dahm@khl.com
Mike Posener Sales Manager Tel: +353 860 431 219 E-mail: mike.posener@khl.com
CONNECT WITH SOCIAL MEDIA