Mammoet completes petrochemical job

By Christian Shelton21 May 2018

Heavy lift and transportation specialist Mammoet completed the demolition and replacement of five heater furnaces in what it described as a “congested” 86-year-old petrochemical plant in Texas City, Texas, USA.

DJI_0003

According to Mammoet, the dimensional constraints in the refinery made crane construction challenging as there was no space to lay down the booms and jibs to assemble the two CC 8800 lattice boom crawler cranes it needed to use for the job.

DJI_0057

Mammoet’s solution was to assemble the two CC 8800s in the air, using two other cranes to lift the jibs and booms. This, Mammoet said, enabled it to salvage and install larger sections of the furnaces, cutting the project’s duration by more than a month.

Once assembled the two CC 8800s were on the site for several months and carried out more than 50 critical lifts.

 

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Long Reads
Post-pandemic demand lengthens delivery times for construction equipment
Government stimulus measures following the global pandemic have led to a surge in demand for construction equipment
Technology paves the way for driving 3D development
What is 3D modelling and what is it used for? Discover more at SC&RA Workshop
PREVIEW: SC&RA Crane & Rigging Workshop
The 2021 Crane & Rigging Workshop will be held September 14-16 at the Hyatt Regency Chicago, USA
CONNECT WITH THE TEAM
Alex Dahm Editor, International Cranes and Specialized Transport Tel: +44(0) 1892 786 206 E-mail: alex.dahm@khl.com
Mike Posener Sales Manager Tel: +353 860 431 219 E-mail: mike.posener@khl.com
CONNECT WITH SOCIAL MEDIA