Kahl Schwerlast relocates gantry crane

By Laura Hatton30 July 2014

Goldhofer PST heavy-duty modules were used to rotate and reposition Duisburg Harbour’s 630 tonne por

Goldhofer PST heavy-duty modules were used to rotate and reposition Duisburg Harbour’s 630 tonne portal crane

A 630 tonne dockside gantry crane was relocated as part of Duisburg Harbour's upgrade in Duisburg, Germany.

The upgrade will increase the harbour's container handling capacity from 1 million standard containers to five million, a spokesperson said. To help achieve this, four additional container cranes, an extra 13 hectares of shipment and storage area, and the relocation of the gantry crane, is to be carried out.

Kahl Schwerlast, main contractor for the project, moved the 630 tonne Trimodal gantry crane from its original location parallel to the quayside to Logport 1 using two six-axle and two four-axle self-propelled transport modules from the Goldhofer PST/SL-E series.

The self propelled modules have hydrostatic drive, electronic multi-way steering and a payload of 45 tonnes per axle line. To increase the payload, the two four-axle modules were combined with three-axle THP heavy-duty modules, a spokesperson added. Power was supplied by four power packs with an output of 155 kW (210 PS) and 360 kW (490 PS).

The crane was 139 metres long, 20 m wide and 18 m high. It was turned 90 degrees to create a waterside outreach of a 15 m, a spokesperson said. Tim Kruse, who helped manage the project, said, “That was a special challenge for us. Manoeuvring a crane of that size in such a tight space with almost centimetre precision is a tall order.

“Manoeuvring so close to the quayside is always a little bit dangerous. So the six additional THP axles provided a margin of safety that permitted us to slightly reduce the axle load on the individual PST modules.”

To relocate the gantry, the crane was raised 300 mm and rotated 90 degrees using the modules, before being repositioned on girders. Once in place, eight heavy-duty cranes were used to lift the portal crane into its final position. The harbour was closed during the process.

“With the Goldhofer PST modules, we are perfectly equipped to handle really heavy outsized loads with almost centimetre precision,” Kruse added.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Long Reads
Post-pandemic demand lengthens delivery times for construction equipment
Government stimulus measures following the global pandemic have led to a surge in demand for construction equipment
Technology paves the way for driving 3D development
What is 3D modelling and what is it used for? Discover more at SC&RA Workshop
PREVIEW: SC&RA Crane & Rigging Workshop
The 2021 Crane & Rigging Workshop will be held September 14-16 at the Hyatt Regency Chicago, USA
CONNECT WITH THE TEAM
Alex Dahm Editor, International Cranes and Specialized Transport Tel: +44(0) 1892 786 206 E-mail: alex.dahm@khl.com
Mike Posener Sales Manager Tel: +353 860 431 219 E-mail: mike.posener@khl.com
CONNECT WITH SOCIAL MEDIA