Gantries and SPMTs install giant gas scrubber

By Niamh Marriott23 May 2023

Engineered Rigging (ER) developed a lift plan to use an Enerpac SBL500 hydraulic gantry system, equipped with the SSU300 hydraulic side shift units, to install a 27 metre long, 120 tonne gas scrubber at the ENAP Aconcagua Refinery in Chile.

Engineered Rigging’s heavy lifting experts assembled the SBL500 gantry crane (Photo: Engineered Rigging)

DSV Global Transport and Logistics (DSV) needed to transport the scrubber to the crude oil refinery, which processes most of the fuels consumed in the Valparaíso region of Chile. Although DSV had a plan for delivering the scrubber, it required assistance determining the best method to offload the enormous device from its transport vehicle and place it in storage. Engineered Rigging identified equipment for the manoeuvre.

Gantry crane construction

Engineered Rigging’s heavy lifting experts mobilized the SBL500 from the Santiago yard. The team assembled the gantry, which features an octagonal boom for added strength and increased capacity and lifting height.

Three technicians assembled and tested the SBL500 hydraulic gantry, while a crew of four assembled and tested a Goldhofer SPMT. (Photo: Engineered Rigging)

Using the gantry’s Intelli-Lift wireless control system, the operator remotely lifted the scrubber from DSV’s specialized transport system and lowered it onto static storage stands. ER’s team then disassembled the gantry and returned with it to Santiago.

“It took us just 4 days to build the gantry, offload the scrubber and deconstruct the gantry for transport back to our yard,” said Arnol Salicetti, Engineered Rigging’s director of South America equipment rentals and sales.

Meanwhile, the general contractor, Echeverria Izquierdo Montajes Industriales (EIMISA), had completed its preparations for installing the new equipment within the refinery. It needed to move the scrubber from the storage stands to its permanent location inside the plant. EIMISA chose Engineered Rigging for the final portion of the project.

Assembly time

Three technicians assembled and tested the SBL500 hydraulic gantry, while a crew of four assembled and tested a Goldhofer self-propelled modular transporter (SPMT) provided by ER’s South American partner Tecnogruas. The Engineered Rigging team then hoisted the scrubber from the storage stands and lowered it onto two Goldhofer PST/SL-E six-axle SPMTs, each powered by individual power units. The gantry was then repositioned next to the crane that would place the scrubber in its final site within the plant.

“The ENAP Aconcagua Refinery is a critical component of the Valparaíso region’s fuel infrastructure,” said Salicetti. “Engineered Rigging’s safe and efficient transport of the scrubber helped the refinery keep fuel flowing as it processed up to 104,000 barrels of crude oil per day.”

Specialized transport

In a single day, the Engineered Rigging heavy lifting team transported the scrubber 1 kilometre within the refinery. This distance included a delicate 90-degree turn, which required each SPMT and associated power pack unit to operate independently of each other. This type of turn is only possible with the nimble SPMT, which can move forward, backwards and sideways.

ER technicians then used the SBL500 hydraulic gantries to offload the scrubber from the SPMTs.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Long Reads
What are the latest boom truck models hitting North America?
ACT spoke with several manufacturers to learn more.
Talking Tadano: Sitting down with Toshiaki Ujiie and Dean Barley
Tadano’s Toshiaki Ujiie and Dean Barley discuss ConExpo, innovation and much more.
Load control is vital for crane safety
Jeff Donaldson discusses why it’s time to create a safer rigging work environment using technology.
CONNECT WITH THE TEAM
Alex Dahm Editor, International Cranes and Specialized Transport Tel: +44(0) 1892 786 206 E-mail: alex.dahm@khl.com
Mike Posener Sales Manager Tel: +353 860 431 219 E-mail: mike.posener@khl.com
CONNECT WITH SOCIAL MEDIA