Mammoet moves entire bridge section

By Niamh Marriott21 June 2022

SEH Engineering contracted Mammoet to move a new bridge section of the Rhine Bridge, in Leverkusen in Germany, 300 metres to its installation position.

The bridge section weighed 1,100 tonnes (Photo: Mammoet)

As the bridge section weighed 1,100 tonnes, and was 66 metres by 34 metres, the highway had to be fully closed.

The new bridge aims to increase traffic volumes on the highway with its new 8 lane structure.

Mammoet used several of its Mega Jack 500 systems, gantry girders and three units of 24 axle lines of self propelled modular transporter (SPMT).

Engineering moves
The simplest approach – stacking the bridge section on the abutment benches using climbing jacks – could not be used because the bridge has a slope in both its the longitudinal and transverse directions. 

This would mean the abutment benches would be both at an angle and at different end heights.

Four towers of Mammoet’s Mega Jack 500 system were used for the job (Photo: Mammoet)

This approach would also require a longer road closure, so the engineering teams worked together to develop a different solution.

Mammoet’s method was to lift, transport and set down the bridge section, all in one manoeuvre.

Four towers of the Mega Jack 500 system were used. The equipment lifted the load via the insertion of successive cassettes at ground level, which reduced manual handling and the need to work at height.

Accessibility issues
Due to a hole in the ground at the pre-assembly site, the bridge section was not accessible to the SPMT.

Mammoet used three units of 24 axle lines of SPMT for the transport (Photo: Mammoet)

The hole was needed for a pillar of the bypass bridge. Instead of filling and covering the hole, it was more efficient to slightly change the position of the bridge section.

So, Mammoet’s team moved the bridge section one metre just before execution.

The repositioned bridge segment was then lifted with four climbing jacks so that the SPMT could be driven underneath. 

The gantry girders and Mega Jack 500 towers were then erected on the SPMT.

The bridge section was manoeuvred 300 metres across the confined site to the installation location, then lifted several metres further so that it could be driven over the abutments of different heights, before being lowered and installed.

Bridge bottlenecks

The bridge section was manoeuvred 300 metres across the confined site to the installation location (Photo: Mammoet)

The new replacement Rhine bridge in Leverkusen is one of the largest infrastructure construction projects in North Rhine-Westphalia.

It is scheduled for completion at the end of 2023 and aims to eliminate traffic bottlenecks.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Long Reads
Crane pad and mat makers discuss trends and issues
Ground stabilization is among the most critical elements of safe crane operation.
What is the demand for telescopic crawlers in North America?
Telescopic crawler models are getting bigger and better, while serving as a fleet necessity.
The Liebherr Group: A German success story
Liebherr the company and Liebherr the family, as well as the company’s presence at Bauma, are legendary in the world of cranes, construction equipment, aerospace technologies and even hotels.
CONNECT WITH THE TEAM
Alex Dahm Editor, International Cranes and Specialized Transport Tel: +44(0) 1892 786 206 E-mail: alex.dahm@khl.com
Mike Posener Sales Manager Tel: +353 860 431 219 E-mail: mike.posener@khl.com
CONNECT WITH SOCIAL MEDIA