Sarens performs heavy lifting operations at a power plant in Selangor, Malaysia
Equator Engineering Sdn. Bhd. (EESB) asked Sarens to perform heavy lifting operations at its plant in Selangor, Malaysia. The scope of the project included:
- Installation of two units of HRSG-OT modules
- Installation of Generator & Turbine
Installation of the HRSG modules was completed this past month and the installation of the generator and turbine is scheduled for September 2022.
For the HRSG modules having a maximum weight of 90T, the team used:
- 10 units of 46/62T strand jacks.
- 5 units of lifting beams designed specifically for the project
The equipment was transported on-site by road from Sarens yard in Balakong.
Sarens designed a lifting system in-house for the project. The design and the equipment had to be inspected and approved by the Department of Occupational Safety and Health (DOSH) of Malaysia before releasing the PMA certificates for the equipment. All the approvals had to be in place within a tight schedule. The equipment was installed and operated on top of a tower, 35m above ground level.
For the next phase starting this September, Sarens will be installing generator and turbine units using modular strand jacks and gantry system.
Sarens crew successfully completed the operation safely and adhering to all the safety procedures. According to Tim Van Hoeydonck, Operations Manager, “Sarens has a proven experience of installing generators and turbines for similar power plants, however this was the first time we installed the HRSG OT modules, which provides us an edge to execute similar projects in the future.